Supreme Court Order Against the Installation of Transmission Tower

LAHURNIP
LAHURNIP
Updated on April 10, 2026

The Supreme Court has issued an interim order against the installation of a power transmission line tower .

The Nepal Electricity Authority has started installing the tower without compensation and consultation on the land of the affected person in Arjundhara Municipality – 2, Jhapa, Province No.1. The court has ordered Nepal Electricity Authority and relevant government institutions not to carry out the installation without providing compensation.

The 11000 V electric power line is going to be constructed from Khujunabari to Sanischari of Jhapa district. The order was issued on 14 August 2022.

Advocate Bhim Rai from LAHURNP provided legal support to the affected.